PRODUCTION
SCHEDULING
Scheduling
and controls are the key to on time performance
on large contracts. Ecodyne Heat Exchangers production scheduling uses the following
methods:
- Engineering
and Manufacturing schedules based on computer estimates of man-hours
per operation. These schedules are updated based upon changes in the
scope of supply impacting man-hours.
- Materials
schedules identifying purchased and inventories materials from master
bills of materials.
- "Production
Ship Schedule" maintained six to nine months into the future to
track key milestones. This schedule is updated weekly.
- Assignment of
a Project Manager to each project with the responsibility to
monitor the progress of the order through Engineering, Procurement and
Manufacturing. The Project Manager functions as the liaison between
the internal departments of the company and the customer, to assure
all contractual obligations are met.
|